ENTERGY FACES 7 TO 8-MONTH DELAYS IN RECEIPT OF TRANSFORMERS

Dear Members,

As you may know, the construction industry has critical supply issues. Entergy is facing lead time delays of seven to eight months for transformers. The Growth Coalition has been meeting with developers and Entergy to better understand the challenges going forward.  After several meetings, developers and builders have gathered information in the region concerning ongoing developments.

This information is being used to better coordinate with Entergy to supply transformers to those developments in which the need is critical.  If you have already provided this information, you can disregard this request.

           

For those that have ongoing developments or buildings in need of placement of transformers, please respond by providing the information requested on the excel spreadsheet.

The Growth Coalition is working to coordinate this effort. Please return this information as quickly as possible. The Growth Coalition will continue to work through this supply train shortfall.

Please email the form to: office@growthcoalition.com

Placement of Transformers Information Spreadsheet